CVHE Compressor Disassembly/Reassembly
作者:管理员 发布于:2014-3-23 23:04:09 点击量:

 

 
 
 
 

Unit Model Number机组型号:____________________________________________
Unit Serial Number机组序列号:___________________________________________
Reason for Teardown大修原因:___________________________________________

 

 
Disassembly  拆卸= 1-36
Ref #
Clearances & Torque’s  
间隙与力矩
 
Reassembly  组装 = (1)-(36)
 
Nominal
额定
Disassembly
拆卸
Reassembly
组装
1. Remove tang operator, 1st stage vane assembly. 拆除导叶执行器,1级导叶组件
 
 
 
 
1
 
 
 
 
 
 
 
 
 
(36). Install tang operator, 1st stage vane assembly安装导叶执行器,1级导叶组件
 
 
 
 
 
 
 
 
(36a). CAPSCREW TORQUE 螺栓力矩
14 Ft Lbs.
 
____Ft Lbs.
2. Remove 1st stage inlet vane assembly.拆除1级进气导叶组件
 
 
2
 
 
 
 
 
 
 
 
(35). Install 1st stage inlet vane assembly.安装1级进气导叶组件
 
 
 
3. Measure 1st stage impeller nose seal clearance. (Radial)检测1级叶轮端部密封间隙 ---径向
 
 
 
________”
(See Table 1)
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
 
 
 
(34). Measure/set 1st stage impeller nose seal. 检测/设置1级叶轮端部密封
 
A
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
(34a). NOSE SEAL BOLT TORQUE端部密封螺栓力矩
 
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
4. Remove 1st stage impeller nose seal.拆除1级叶轮端部密封
 
3
 
 
 
(33). Install 1st stage impeller nose seal.安装1级叶轮端部密封
 
 
 
 
5. Remove 1st stage suction cover拆除1级吸气蜗壳
 
 
 
 
 
(32). Install 1st stage suction cover安装1级吸气蜗壳
 
4
 
 
 
(32a). SUCTION COVER BOLT TORQUE.吸气蜗壳螺栓力矩
 
 
150 Ft Lbs.
 
             ____Ft Lbs.
6. Measure 1st stage impeller nose runout.检测1级叶轮端部径向跳动
 
A
 
< 0.0035”
 
______” TIR
 
(31). Measure 1st stage impeller nose runout.检测1级叶轮端部径向跳动
 
 
 
 
______” TIR
7. Measure detail “A” clearances for 1st stage impeller.检测1级叶轮间隙---参看备注A
( See Page 6参看第6) 
S
 
 
R
 
Flush/+0.005”
 
0.022” min radial centered
_________”
 
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
 
 
 
 
 
 
 
Disassembly 拆卸 = 1-36
Ref #
Clearances & Torque’s
 
Reassembly   组装= (1)-(36)
 
Nominal
Disassembly
Reassembly
8. Remove impeller lock nut, lockwasher & spring washer. 拆除叶轮防松螺母、防松垫圈及弹簧垫圈
 
 
 
 
(30). Install impeller lock nut, lockwasher & spring washer.安装叶轮防松螺母、防松垫圈及弹簧垫圈
5
 
 
 
(30a). LOCKNUT TORQUE防松螺母力矩
 
115 Ft Lbs.
 
_____Ft Lbs.
9. Remove 1st stage impeller 拆除1级叶轮
 
 
6
 
 
 
(29). Install 1st stage impeller. 安装1级叶轮
 
 
 
 
10. Measure shaft runout.检测轴径向跳动
 
<0.0012” TIR
______” TIR
 
11. Measure 1st stage shaft seal clearance. 检测一级轴封间隙
 
 
B
 
0.018/0.024”
(Radial)
 
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
(28). Measure/set 1st stage shaft seal clearance. 检测/设置1级轴封间隙
 
 
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
 
 
(28a). SHAFT SEAL BOLT TORQUE轴封螺栓力矩
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
12. Remove 1st stage shaft seal. 拆除1级轴封
 
 
7
 
 
 
(27). Install 1st stage shaft seal. 安装1级轴封
 
 
 
 
(26). Measure/set detail “A” clearances for 1st stage impeller. 检测/设置1级叶轮间隙---参看备注A
 
S
 
 
R
 
Flush/+.005”
 
0.022” min
radial
centered
 
 
_________”
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
(26a). DIFFUSER PLATE BOLT TORQUE. 扩压平板螺栓力矩
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
13. Remove 1st stage shaft impeller spacer拆除1级叶轮定距轴套
 
8
 
 
 
(25). Install 1st stage shaft impeller spacer.安装1级叶轮定距轴套
 
 
 
 
14. Remove 1st stage diffuser plate.拆除1级扩压平板
 
9
 
 
 
(24). Install 1st stage diffuser plate.安装1级扩压平板
 
 
 
 
15. Remove 2nd stage shroud assembly. 拆除2级吸气盖板
 
 
 
 
(23). Install 2nd stage shroud assembly. 安装2级吸气盖板
10
 
 
 
(23a). 2ND STAGE SHROUD BOLT TORQUE. 两级吸气盖板螺栓力矩
 
 
6 Ft Lbs.
 
 
_____Ft Lbs.
16. Measure 2nd stage impeller nose seal clearance. 检测2级叶轮端部密封间隙
 
 
 
C
 
_______”
(See Table 1)
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
(22). Measure/set 2nd stage impeller nose seal clearance. 检测/设置2级叶轮端部密封间隙
 
 
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
 
 
(22a). NOSE SEAL BOLT TORQUE端部密封间隙螺栓力矩
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
 
 
 
 
 
 
 
Disassembly   拆卸 = 1-36
Ref #
Clearances & Torque’s
 
Reassembly    组装 = (1)-(36)
 
Nominal
Disassembly
Reassembly
17. Remove 2nd stage impeller nose seal. 拆除2级叶轮端部密封
 
 
 
 
(21). Install 2nd stage impeller nose seal. 安装2级叶轮端部密封
11
 
 
 
18. Remove 2nd stage suction cover.
 拆除2级吸气涡壳
 
 
 
 
(20). Install 2nd stage suction cover.
 安装2级吸气蜗壳
12
 
 
 
(20a). SUCTION COVER BOLT TORQUE. 2级吸气涡壳螺栓力矩
 
 
150 Ft Lbs.
 
 
_____ Ft Lbs.
19. Measure 2nd stage impeller nose runout. 检测2级叶轮端部径向跳动
 
 
< 0.0035’ TIR
 
______” TIR
 
(19). Measure 2nd stage impeller nose runout.检测2级叶轮端部径向跳动
C
 
 
 
______” TIR
20. Measure detail “A” clearances of 2nd stage impeller. 检测2级叶轮间隙---参看备注A
(See Page 6 参看第6)
 
 
S
 
R
 
 
Flush/+.005”
 
0.022” min
radial
centered
_________”
 
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
21. Remove 2nd stage impeller. 拆除2级叶轮
 
13
 
 
 
(18). Install 2nd stage impeller. 安装2级叶轮
 
 
 
 
22. Measure 2nd stage shaft seal clearance.检测2级轴封间隙
 
 
 
0.018/0.024”
(Radial)
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
(17). Measure/set 2nd stage shaft seal clearance. 检测/设置2级轴封间隙
 
D
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
 
 
(17a). SHAFT SEAL BOLT TORQUE轴封螺栓力矩
 
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
23. Remove 2nd stage shaft seal. 拆除2级轴封
 
14
 
 
 
(16). Install 2nd stage shaft seal.安装2级轴封
 
 
 
 
(15). Measure/set detail “A” clearances of 2nd stage impeller. 检测/设置2级叶轮间隙---参看备注A
(See Page 6 参看第6)
 
 
 
S
 
R
 
 
 
Flush/+.005”
 
0.022” min
radial
centered
 
 
_________”
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
(15a). 2ND STAGE DIFFUSER BOLT TORQUE. 2级扩压平板螺栓力矩
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
 
24. Remove 2nd stage shaft impeller spacer.拆除2级叶轮定距轴套
 
15
 
 
 
(14). Install 2nd stage shaft impeller spacer. 安装2级叶轮定距轴套
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Disassembly 拆卸 = 1-36
Ref #
Clearances & Torque’s
 
Reassembly   组装 = (1)-(36)
 
Nominal
Disassembly
Reassembly
25. Remove 2nd stage diffuser plate.拆除2级扩压平板
 
 
16
 
 
 
(13). Install 2nd stage diffuser plate安装2级扩压平板
 
 
 
 
26. Remove 3rd stage vane operator assembly.拆除3级导叶执行器组件
 
 
 
 
(12). Install 3rd stage vane operator assembly. 安装3级导叶执行器组件
17
 
 
 
(12a). VANE OPERATOR BOLT TORQUE导叶执行器螺栓力矩
 
60 Ft Lbs. or
gkt extrudes
 
 
_____ Ft Lbs.
27. Remove 3rd stage shroud and vane assembly.拆除3级吸气盖板及导叶组件
 
 
 
 
(11). Install 3rd stage shroud and vane assembly. 安装3级吸气盖板及导叶组件
18
 
 
 
(11a). 3RD STAGE SHROUD BOLT TORQUE三级吸气盖板螺栓力矩
 
 
6 Ft Lbs.
 
 
_____ Ft Lbs.
28. Measure 3rd stage impeller nose seal clearance.检测3级叶轮端部密封间隙
 
 
______”
(See Table 1)
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
(10). Measure/set 3rd stage impeller nose seal clearance. 检测/设置3级叶轮端部密封间隙
E
 
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
 
 
(10a). NOSE SEAL BOLT TORQUE端部密封间隙螺栓力矩
 
 
 
24 Ft Lbs.
 
 
____Ft Lbs.
29. Remove 3rd stage impeller nose seal.拆除3级叶轮端部密封
 
19
 
 
 
(9). Install 3rd stage impeller nose seal. 安装3级叶轮端部密封
 
 
 
 
30. Remove 3rd stage suction cover casing.拆除3级吸气蜗壳
 
 
 
 
(8). Install 3rd stage suction cover casing.安装3级吸气蜗壳
20
 
 
 
(8a). SUCTION COVER BOLT TORQUE三级吸气蜗壳螺栓力矩
 
 
150 Ft Lbs.
 
 
_____ Ft Lbs.
31. Measure 3rd stage impeller nose runout.检测3级叶轮端部径向跳动
 
E
 
< 0.0035” TIR
 
______” TIR
 
(7). Measure 3rd stage impeller nose runout. .检测3级叶轮端部径向跳动
 
 
 
 
______” TIR
32. Measure detail “A” clearances of 3rd stage impeller. 检测三级叶轮间隙---参看备注A
(See Page 6参看第6)
 
 
 
S
 
R
 
 
 
Flush/+.005”
 
0.022” min
radial
centered
 
_________”
 
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
(6). Install 3rd stage and impeller.安装3级叶轮
 
 
 
 
 
 
 
 
 
 
 
Disassembly   拆卸 = 1-36
Ref #
Clearances & Torque’s
 
Reassembly    组装 = (1)-(36)
 
Nominal
Disassembly
Reassembly
33. Remove 3rd stage impeller. 拆除3级叶轮
 
 
21
 
 
 
34. Measure bearing oil seal clearance.检测轴承油封间隙
 
 
 
F
 
0.002/0.004”
(Radial)
12 Hr ______”
6 Hr _______”
3 Hr _______”
9 Hr _______”
 
 (5). Measure/set bearing oil seal clearance.检测/设置轴承油封间隙
 
 
 
0.002/0.004”
(Radial)
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
(5a). OIL SEAL BOLT TORQUE油封螺栓力矩
 
24 Ft Lbs.
 
 
 
_____ Ft Lbs.
(4). Measure/set detail “A” clearances of 3rd stage impeller. 检测/设置3级叶轮间隙---参看备注A
(See Page 6 参看第6) 
 
S
 
 
 
R
Flush/+.005”
 
0.022” min
radial
centered
 
 
_________”
 
12 Hr ________”
6 Hr _________”
3 Hr _________”
9 Hr _________”
 
(4a). DIFFUSER PLATE BOLT TORQUE 扩压平板螺栓力矩
 
 
24 Ft Lbs.
 
 
 
 
_____Ft Lbs.
35. Remove bearing oil seal and gasket. 拆除轴承油封及垫圈
 
22
 
 
 
(3). Install bearing oil seal and gasket 安装轴承油封及垫圈
 
 
 
 
 
36. Remove bearing oil seal mounting plate and gasket.拆除轴承油封固定盘及垫圈
 
 
 
 
(2). Install 3rd stage diffuser plate,bearing oil seal mounting plate and gasket.安装3级扩压平板,轴承油封固定盘及垫圈
23
 
 
 
(2a). SEAL MOUNTING BOLT TORQUE油封固定盘螺栓力矩
 
 
24 Ft Lbs.
 
 
_____Ft Lbs.
 
 
(1). Measure motor shaft runout检测电机轴径向跳动
 
 
< 0.0012” TIR
 
 
_____” TIR

 


 

CVHE/F/G 止推轴承安装/拆卸程序
 
 
 
 
 
 
 
 
机组型号:
 
机组编号:
 
更换轴承原因:
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
警告:小心电气伤害
进行此项工作或者在其它电器设备上进行操作之前,一定要切断电源。否则可能会由于电机或者部件转动造成严重的人身伤害甚至死亡
 
 
 
 
 
 
 
 
 
 
 
拆卸
 
 
 
第1步
释放压缩机的压力或真空、回收内部充注物
 
 
如果压缩机安装在机组上,要先将冷媒回收,然后将机组抽真空并充干燥氮气
 
 
 
 
 
 
 
 
第2步
在轴承端盖上钻两个1/4英寸的孔
 
 
拆卸电机或压缩机时为了保证部件找准定位,在轴承端盖上钻两个1/4英寸的孔以便在拆卸时安装导杆。
 
 
 
 
 
 
 
 
第3步
拆除供油管和排油管
 
 
 
拆除供油管和排油管。如果需要(用管割刀)切断管路,应首先用砂纸祛除管路上的油漆。
工作期间所有开口必须包扎以防止杂质进入润滑系统
 
 
 
 
 
 
 
 
第4步
拆除轴承视镜板
 
 
拆除轴承视镜板。拆除旧的O型圈并清洗密封面。
 
 
 
 
 
 
 
 
第5步
拆除止推轴承的防松螺母和锁紧垫圈
 
 
拆除止推轴承的锁紧垫圈和防松螺母。扳平锁紧垫圈的突舌,用套管扳手和套管工具拆除防松螺母。
 
 
 
 
 
 
 
 
第6步
拆除轴承端盖的两个螺栓并安装两根导杆
 
 
松开轴承端盖固定螺栓。拆除两个螺栓并用两根导杆代替,用于支撑轴承端盖和电机轴的重量。
 
 
 
 
 
 
 
 
第7步
拆除轴承固定螺栓及轴承环
 
 
拆除四个9/16英寸的螺栓以及轴承环。
 
 
 
 
 
 
 
 
第8步
拆除轴承密封板的所有六角螺栓
 
 
拆除八个3/8-16英寸固定轴承密封的六角螺栓
 
 
 
 
 
 
 
 
第9步
拆除轴承端盖剩余的螺栓
 
 
拆除固定轴承端盖的螺栓。其中有两个短螺栓是用于电气端子盒,要注意做好标记以便正确安装。
 
 
 
 
 
 
 
 
第10步
从轴承套上分离轴承端盖
 
 
 
在定位螺栓孔中安装三根导杆以便拆卸轴承端盖板。将其它螺栓在容器中放好。缓慢均匀地转动导杆,
将轴承端盖板从外侧滚珠轴承中分离出来。
 
 
 
 
 
 
 
 
第11步
拆除轴承端盖
 
 
 
用U形钩或吊环起吊轴承端盖。轴承端盖必须从上部支撑(用吊带或类似的东西)。轻轻地前后移动将轴承端盖从轴承套上分离出来。(在轴承端盖移出大概1/2英寸时)密封面拆除后拆除轴承端盖时会稍稍往下掉。
 
警告:当心重物砸伤。
不要在倒链螺栓孔上使用吊环。吊环不是用于水平起吊的,否则可能会断裂造成伤害。
第12步
移走轴承端盖
 
 
一但密封面拆除轴承端盖会下降直至转子支撑在定子上(参见警告)。将轴承端盖完全拆除。
 
警告:当心损坏定子
要特别小心避免轴承端盖卡在轴承上,也要避免转子移动造成对定子组件的损坏。
警告:小心眼睛和头受伤
轴承端盖拆除后要立即拆除导杆,防止人走近而受伤
 
 
 
 
 
 
 
 
第13步
拆除止推轴承
 
 
 
 
 
 
 
 
用拉轴承的专业工具拆除止推轴承。工具要安装在轴承内侧轴承套的后侧以防止损坏轴承和轴。拆卸轴承时要特别注意以下事项:
(a)拉轴承的工具要与轴匹配
(b)工具必须安装在内侧轴承套上
(c)轴承不允许掉在轴或工具上,在轴上包一些绝缘胶带以保护轴是一个比较好的方法。
(d)不要通过加热轴承的方法来拆卸轴承,这样会损坏轴承和电机。
(e)要用吊索或吊链支撑拉轴承的工具的重量
 
警告:小心损坏轴
在移动止推轴承时要格外小心不要损坏轴肩和轴颈。
 
 
 
 
 
 
 
 
第14步
拆除内侧轴封
 
 
 
拆除内侧轴封。小心不要损坏衬垫,并留意密封的底部有一个排油孔。对此必须做好标记以保证安装时排油孔位于底部。面对电机时轴承盖上的V形切痕应位于顶部。
 
 
 
 
 
 
 
 
 
 
 
安装
 
 
 
第15步
更换内侧轴封
 
 
 
更换内侧轴封,电机轴上的垫圈换新。要确保排油孔位于底部、V形切痕位于顶部
 
第16步
确认轴承与轴是否相配
 
轴的大小


     
 
 
更换CVHE/F/G的止推轴承时,要严格确认轴的设计类型。确认轴的设计类型的唯一可靠方法是从轴的末端看是否有"K4"标记。轴末端的"K4"标记尺寸变化范围在1/4英寸到1/16隐村高。如果轴没有更换过,设计序列号可以确定轴的设计类型。
 
 
 
 
 
 
 
 
 
 
 
 
第17步
检查轴和旧轴承是否有损坏或磨损
 
轴的尺寸


     
 
 
拆除止推轴承以后,检查轴是否有损坏或磨损,尤其是轴颈和轴肩部分。要检测轴肩部分的外径以确定是否在公差范围内(参看CVHE-SB-33A)。如果超出公差范围,轴需要拆卸校整或更换。
 
 
 
 
 
 
 
 
 
 
 
安装轴承
 
 
 
第18步
检查轴承是否配套
 
轴承序列号

        A
        B


     
 
 
 
轴承要配套才能安装。配套的轴承的序列号相同,但其中一个轴承的序列号后面跟了一个字母。
 
警告:放置安装前损坏轴承
除非绝对必要,不要清洗轴承。轴承清洗后要特别注意将溶剂和清洁剂清除干净。
 
 
 
 
 
 
 
 
 
第19步
加热轴承
 
 
 
轴承要均匀加热到230℉至250℉。如果用感应加热器加热,安装前轴承要消磁。取出轴承之前要确认感应加热器已经关闭。
 
 
 
 
 
 
 
 
注:CVHE/F/G可以使用两种轴承。要根据不同供应商提供的轴承选择下面的一种安装步骤。不要两种都用。
 
 
 
 
 
 
 
 
 
安装NTN轴承
安装SKF轴承
 
 
 
 
 
 
 
 
20
检查每个轴承是否有顶点标记
检查轴承的定为标志
 
 
 
 
顶点标记通常是标记在每个轴承的内圈和外圈上的
圆圈或凹陷。没有顶点标记的轴承应该予以退货。
有一个V字形标记位于两个轴承的外圈,每个轴承上
一半。另外每个轴承的内圈上也有一条线。当两个轴承在轴上的位置安装正确后,轴承外圈的标记就会组成一个完整的
V字,内圈的线也会连成一条直线
 
 
 
 
 
 
 
 
 
21
安装内侧轴承
安装内侧线轴承
 
 
 
将轴承外圈比较薄的一侧对准轴,将轴承套到轴上,直到轴承座顶住轴肩为止。

将轴承的顶点标记置于轴的上部
将轴承外圈比较薄的一侧对准轴,将轴承套到轴上,直到轴承座顶住轴肩为止。

用油性尖笔在轴承内圈的侧面做一条标记线。标记线应在轴的下方。
 
 
 
 
 
 
 
 
22
将轴承内外圈顶点标记对齐
安装内侧线轴承
 
旋转已安装轴承的外圈直到内外圈的顶点标记成一直线为止。
旋转轴承的外圈,将外圈上的V字形标记旋转至内圈标记线的另一侧。
 
 
 
 
 
 
 
 
 
 
23
安装外侧轴承
安装外侧轴承
 
 
 
将外侧轴承安装到轴上之前要将轴承内外圈的顶点标记对齐。让外侧轴承的顶点标记与内侧轴承的顶点标记成160°至200°的角度,将外侧轴承套到轴上。
将外侧轴承套到轴上之前要将轴承外圈的部分V形标记和内圈上的直线标记对好。保持轴承的定位标记与内侧轴承的定位标记成一直线,将轴承安装到轴上。
 
 
 
 
 
 
 
 
第24步
将轴承就位
 
 
 
 
 
 
 
 
(a)将外侧轴承内圈推到顶住内侧轴承为之,直到轴承在轴上卡紧。让轴承冷却到100F以下。在轴上安装一个气动螺母,用手拧紧螺母滑块端直到螺母顶紧外侧轴承为止。
(b)将气动管连接到气动螺母上,用一个带压力调节阀的气泵给螺母吹空气加压到2200psi使轴承顶住轴肩。
(c)用.001英寸的塞尺测量轴承圈与轴肩之间的间隙以确定轴承是否安装到位。安装到位的轴承的间隙应该是0.000。
释放气动螺母的压力,并拆除气动管和气动螺母。
 
 
 
 
 
 
 
 
第25步
安装新的垫圈并用手拧紧防松螺母
 
 
 
安装新的垫圈并用手拧紧防松螺母
 
 
 
 
 
 
 
 
第26步
安装轴承密封的丝杆
 
 
 
安装两根16英寸长的3/8"丝杆,并将密封板安装上去。注意密封板的定位,保证排油孔位于底部。不要忘记安装密封圈,并确保密封圈的正确定位。
 
 
 
 
 
 
 
 
第27步
安装轴承端盖
 
 
 
 
 
重新安装先前为了安全起见拆掉的轴承端盖导杆。将轴承端盖的O型圈涂上LocTite 515"Gasket Eliminator"。用起吊设备吊装轴承端盖。轴承端盖应由导杆定位并支撑其重量。
轴承端盖定位时,选择联接内侧密封的导杆穿过端盖的螺栓孔时应使排油孔位于底部。
将轴承端盖安装到位,并用一些螺栓稍稍固定一下。端盖应该用很小的力就可以使其在轴承上滑动。
 
 
 
 
 
 
 
 
 
 
第28步
在拆卸时的钻孔内安装两根导杆并拧紧所有螺栓
 
 
 
在先前拆卸时所钻的孔内重新安装两根导杆。导杆对于保证恢复压缩机拆卸前的密封间隙是非常必要的。用150Ft Lbs.的力矩将所有螺栓拧紧。
第29步
检查轴是否能自由转动
 
 
转动轴,确保没有咬合或卡住的现象
 
 
 
 
 
 
 
 
第30步
安装内侧密封
 
 
 
 
沿导杆将内侧密封推到位并安装内六角螺栓。正确安装的轴承应该高出轴承端盖大约1/16英寸。如果不是,轴承密封没有安装到位,轴承会浮动。这可能会导致的压缩机损坏。必要时要重新安装轴承密封。用24Ft Lbs.力矩拧紧螺栓。
 
 
 
 
 
 
 
 
第31步
检查轴是否能自由转动
 
 
转动轴,确保没有咬合或卡住的现象
第32步
安装轴承环
 
 
 
安装轴承环及螺栓,用24Ft Lbs.的力矩拧紧。参看图21及22。轴承环的作用是给轴承外圈提供一种抓力防止其浮动。
 
 
 
 
 
 
 
 
第33步
检查轴是否能自由转动
 
 
转动轴,确保没有咬合或卡住的现象
 
 
 
 
 
 
 
 
第34步
用力矩扳手锁紧
 
 
 
 
 
 
 
要用合适的力矩扳手和要求的力矩拧紧防松螺母。这对轴直径比较小的机组是可能的。对于大直径的轴,需要用气动套筒扳手以及相应的力矩以防止转子在定子中转动。力矩数据如下:
小直径的轴:60至80 Ft Lbs.
大直径的轴:160至200 Ft Lbs.
不要用榔头或活动扳手拧紧防松螺母。用CVHE-SB-33A表1例举的正确的套管扳手工具及相应的力矩,按照相应的程序完成。
 
 
 
 
 
 
 
 
第35步
锁紧垫圈
 
 
将锁紧垫圈的一个突舌敲弯。
 
 
 
 
 
 
 
 
第36步
安装轴承视镜板
 
 
安装视镜板。O型圈和外侧法兰上一定要涂LockTite 515
 
 
 
 
 
 
 
 
第37步
安装轴承供油管和排油管
 
 
 
重新安装供油管和排油管
注:焊接管路时一定要用惰性气体保护
 
 
 
 
 
 
 
 
第38步
对机组加压检漏
 
 
 